In short: A CVR compares the value earned on a project against the cost incurred, to show the margin and how it is moving. It is only as good as its accruals: unagreed variations carried at full value, cost that has been incurred but not invoiced, and unpriced risk are the three entries that turn a reassuring report into a surprise at the final account.
Cost value reconciliation is the monthly discipline of putting two numbers next to each other: what the project has earned, and what it has cost. The gap is the margin. The direction of travel matters more than the number.
Done properly, a CVR is the earliest warning a business gets. Done loosely, it is the reason a project that reported margin all year lands short at the final account.
The value side
Value is not the same as the certified amount. A CVR should carry:
- certified value to date;
- work done but not yet certified;
- variations submitted and agreed, at agreed value;
- variations submitted and not agreed, at a realistic value, not the claimed value;
- claims for time and money, at a value that reflects the strength of the entitlement and the evidence;
- credits and omissions, deducted.
The fourth and fifth entries are where CVRs go wrong. Carrying an unagreed variation at 100% of what was claimed assumes an outcome nobody has agreed to. Carrying a loss and expense claim at full value before the notices have even been tested assumes more still.
The cost side
Cost has to be complete, which means more than the ledger:
- cost incurred and invoiced;
- cost incurred but not yet invoiced (accruals): materials delivered, labour worked, plant on hire;
- committed cost: orders placed, subcontracts let;
- retention held on the supply chain, and payable to you;
- provisions for known risks: defects, contra charges, agreed liabilities.
Missing accruals flatter a project exactly as much as optimistic value does, and they do it silently: the cost simply arrives a month or two later.
Forecast to completion
The useful part of a CVR is not the position; it is the forecast. Cost to complete, value to complete, and the margin they produce at the end. Comparing this month’s forecast with last month’s tells you whether the project is converging or drifting.
Warning signs
A report worth a second look usually shows one of these:
- margin improving, driven by claims. Value is rising on entitlement that has not been agreed.
- accruals falling while activity is constant. Cost is being missed, not saved.
- a large “work done not certified” balance that never converts. Something is wrong with the application or the account, not just the timing.
- no provision for known contra charges the other side has already raised.
- the forecast that never moves. A margin that is identical for six months has not been calculated for six months.
- the final account that arrives lower than the CVR said all year. By then it is history.
Why it belongs with the commercial function
A CVR is a commercial document with an accounting output. The value entries depend on judgements only the commercial team can make: how strong a variation is, whether a notice was given, whether the delay narrative holds. Prepared away from that knowledge, it becomes an arithmetic exercise on someone else’s assumptions.
That is also why the reporting and the account should agree. If the CVR is carrying entitlement that never appears in the final account, or the account claims what the CVR never recognised, one of them is wrong.