In short: JCT and NEC4 protect the same entitlements by very different routes. JCT runs on variations, relevant events and loss and expense, assessed largely after the fact. NEC4 runs on compensation events, quoted and agreed as they happen, with an eight-week time bar and an accepted programme at the centre of the process. NEC4 tends to cost more in commercial administration during the works but, if administered well, leaves far less to argue about at the end.
Many subcontractors work under both forms of contract. They both protect broadly the same entitlements, but they get there differently; the project management teams need to ensure the processes are understood and implemented correctly to avoid the risk of non-payment developing.
Change: variations or compensation events
JCT treats change as a variation: instructed, then valued using the contract’s valuation rules, often after the work is completed. Valuation timelines can be open-ended and often remain open until the final account stage of the contract.
NEC4 treats change as a compensation event: notified, quoted, agreed and implemented as it happens, using forecast cost where the work is not yet done. Once implemented, the assessment is not revisited simply because the forecast becomes incorrect.
The practical consequence: under JCT, the value is argued at the end; under NEC4, the value is fixed at the time and the outcome determined. Under NEC4 the quality of your quotation is key to the commercial result.
Time bars
This is where NEC4 catches people out. A contractor who does not notify a compensation event within eight weeks of becoming aware of it generally loses the entitlement to more time and money altogether.
JCT has notice requirements too, and amendments frequently make them conditions precedent, but the unamended form does not carry a single hard cliff edge of that kind.
For a subcontractor, the discipline required is different in practice: under NEC4, a notification register with dates of awareness is not administration, it is key to ensuring the entitlement is met.
Programme
NEC4 puts the accepted programme at the centre of its processes. Delay is assessed by comparing planned completion against the accepted programme current at the time of the event. If your programme is out of date or unaccepted, delay assessment gets more complex.
JCT assesses extensions of time against relevant events and the completion date, with more room for retrospective analysis and rather less pressure to keep a formally accepted programme current.
Early warnings
NEC4 requires early warning of anything that could increase cost, delay completion or impair performance, recorded in the early warning register. If you should have given one and did not, a compensation event can be assessed as if you had, which can reduce what is recoverable.
JCT has notification duties but no equivalent collaborative mechanism with that consequence attached.
Payment
Both are subject to the Construction Act, so both have due dates, final dates and notices. The mechanics differ: NEC4 works from assessment dates and, on cost-based options, from Defined Cost with its own record-keeping demands; JCT works from interim valuation dates and the valuation rules.
Either way, the payment notice discipline is the same, and missing it has the same consequence.
Amendments matter more than the form
An unamended form is rare in the supply chain. JCT subcontracts arrive with schedules of amendments; NEC4 arrives with Z clauses. Amendments routinely:
- shorten notice periods, or make them conditions precedent;
- move design responsibility;
- cap or remove entitlement to loss and expense;
- change the payment timetable;
- add termination and set-off rights.
Read the amendments before the form. A contract review that produces a risk register of the amendments is worth more at tender than any general familiarity with the standard form.
What this means for your commercial resource
| JCT | NEC4 | |
|---|---|---|
| Where the effort falls | Later: valuation and claims | Earlier: notifications and quotations |
| Hardest deadline | Contract-specific notice terms | Eight weeks to notify a compensation event |
| Records that decide it | Valuation records, delay evidence | Early warnings, notifications, accepted programme, cost records |
| Biggest risk | Arguing the account at the end | Losing entitlement by notifying late |
Both forms have their pros and cons. But NEC4 demands commercial attention while the work is happening, and it is a common issue that contractors and subcontractors try to administer it as a traditional JCT contract, leading to significant risk to both parties.
MAG-7 works under JCT, NEC (including NEC4), IChemE and bespoke subcontracts. See subcontractor services. This article is a general comparison of the unamended forms, not advice on any particular contract.