NEC4 Option C: How Compensation Events Are Assessed

  • NEC4
  • Compensation events
  • Target cost

In short: Under NEC4 Option C, a compensation event changes the target (the total of the Prices) and, where it causes delay, the Completion Date. It is assessed as the effect on Defined Cost plus the Fee, using a forecast for work not yet done, and once implemented it is not revisited because the forecast turns out to be wrong. The contractor must notify within eight weeks of becoming aware of the event or risk losing the entitlement.

NEC4 Engineering and Construction Contract (ECC) Option C is a target price contract with an activity schedule. The contractor is paid its actual Defined Cost plus the Fee as the work progresses, and the difference between that and the target (the total of the Prices) is shared between client and contractor at the end, using the share ranges in the Contract Data.

That makes compensation events important under Option C. They do not change what the contractor is paid week to week, because that is still Defined Cost plus Fee. What they change is the target that performance is measured against. An unassessed or under-assessed compensation event can quietly turn a gain share into a pain share.

What is a compensation event?

A compensation event is an event listed in the contract that, if it happens and is not the contractor’s fault, entitles the contractor to have the Prices, the Completion Date and any Key Dates reassessed. The core list is in clause 60.1. Some secondary Options add further events, and the parties can add their own in the Contract Data.

Common examples include:

  • an instruction from the Project Manager changing the Scope;
  • the client not providing access, information or something it is required to provide by the date shown on the Accepted Programme;
  • the Project Manager or Supervisor not replying to a communication within the period the contract requires;
  • physical conditions an experienced contractor would have judged to have such a small chance of occurring that it would have been unreasonable to allow for them;
  • weather measurements more severe than the 1-in-10-year event for that month;
  • a breach of contract by the client.

Step 1: notification

Either party can start the process.

  • The Project Manager notifies compensation events arising from its own instructions or decisions, at the time of the instruction.
  • The contractor notifies any other event it believes is a compensation event.

The contractor must notify within eight weeks of becoming aware that the event has happened (clause 61.3). If it does not, it generally loses its entitlement to a change in the Prices, the Completion Date and Key Dates, unless the event arose from something the Project Manager should have notified but did not. This is one of the most important time bars in NEC4.

Notifying something as a compensation event costs very little. Missing the eight-week window can cost the whole entitlement; it is best to notify early and let the Project Manager decide, seeking the entitlement early to avoid time bar risk.

Step 2: the Project Manager’s response

The Project Manager decides whether the event is a compensation event. If it is, it instructs the contractor to submit a quotation. The contract sets short periods for the Project Manager to respond, and if it fails to respond the contractor can notify that failure. Continued silence can result in the notification being treated as accepted.

Step 3: the quotation

The contractor submits a quotation within three weeks of being instructed to, and the Project Manager replies within two weeks of receiving it (clause 62.3), unless longer periods are agreed. The quotation shows:

  • the proposed change to the Prices, built up from the effect on Defined Cost plus the resulting Fee;
  • any delay to the Completion Date and Key Dates;
  • a revised programme, where the programme is affected.

The Project Manager can accept the quotation, instruct a revised quotation (with reasons), or decide to make its own assessment. If the contractor’s quotation is not answered in time, the contract again provides a route for it to be treated as accepted.

How the change to the Prices is assessed

Assessment follows the rules in clause 63, and the logic is the same whichever main Option is used:

  1. Choose the dividing date. For an event arising from a Project Manager instruction or notification, this is the date of that communication. For other events, it is the date the event was notified.
  2. Work done before the dividing date is assessed using the Defined Cost actually recorded.
  3. Work not yet done is assessed using forecast Defined Cost.
  4. Add the Fee, applying the fee percentage in the Contract Data.
  5. Include risk allowances for matters that have a significant chance of occurring and are at the contractor’s risk, priced as an experienced contractor would.

Under Option C the result changes the target. The activity schedule is updated so that the total of the Prices reflects the event.

How delay is assessed

A delay to the Completion Date is assessed as the length of time that planned Completion is later than planned Completion shown on the Accepted Programme current at the dividing date. That is why a regularly updated, accepted programme matters so much under NEC4: it is the baseline every time-related compensation event is measured against.

Terminal float, the time between planned Completion and the Completion Date, belongs to the contractor. It is not used up by compensation events.

Implementation, and why forecasts matter

A compensation event is implemented when the Project Manager accepts a quotation, notifies its own assessment, or the quotation is treated as accepted. Once implemented, the assessment is not revised because a forecast turns out to be wrong.

This is the single most important commercial point in the process. The quotation is a forecast, and both sides live with it. A contractor that under-forecasts carries the overrun against a lower target. A client that accepts an inflated forecast pays for it through the share mechanism. The quality of the quotation is what protects the position.

Key periods at a glance

Step Period Clause
Contractor notifies a compensation event Within 8 weeks of becoming aware 61.3
Contractor submits quotation Within 3 weeks of instruction 62.3
Project Manager replies to quotation Within 2 weeks of receipt 62.3

Periods shown are the unamended NEC4 ECC defaults. Always check the Contract Data and any Z clauses, which frequently change these periods and the list of compensation events.

Practical points for Option C

  • Keep Defined Cost records clean and current. They are the evidence for the “before” half of every assessment.
  • Keep the Accepted Programme up to date. An out-of-date programme weakens every delay assessment.
  • Use early warnings. Under NEC4, if the contractor did not give an early warning it should have given, the event is assessed as if it had, which can reduce the entitlement.
  • Track every notification against the eight-week time bar in a compensation event register, with dates of awareness recorded.
  • Read the Z clauses before you sign. Amendments that shorten periods, remove compensation events or introduce deemed-rejection provisions change the risk profile of the whole contract. An AI contract review flags them in a risk register.

This article is a general explanation of the unamended NEC4 ECC and is not advice on any particular contract. If you need help with compensation events on a live project, contact mag-7.