In short: Most pay less notices fail for procedural reasons, not commercial ones. The five recurring mistakes are serving late, failing to state the sum and the basis of calculation, serving on the wrong person or by the wrong method, deducting contra charges that were never notified, and saying nothing at all because the account is still being discussed.
A pay less notice is the paying party’s safety net. It is also an easy document on a construction project to get wrong, because it is governed by dates and content requirements that do not consider the strength of your commercial position.
Here are the five failures that come up regularly.
1. Served late
The deadline is whatever the contract sets, and where the contract is silent the Scheme requires the notice not later than seven days before the final date for payment.
A notice served the following day is ineffective. There is no discretion, no “near enough”, and no argument about prejudice. The cure is quick and effective: a notice calendar for every package and every cycle, with the deadline entered as a hard date, counted correctly.
Counting matters more than people expect, because Christmas Day, Good Friday and bank holidays are disregarded when the statutory periods are worked out. Our payment notice calculator does the counting.
2. No sum, or no basis
The notice must state the sum the payer considers due at the date of the notice, and the basis on which that sum is calculated.
“We do not accept your application” is not a pay less notice. Nor is a bare figure with nothing behind it. The basis does not have to be a forensic report, but it does have to let the payee understand how the number was reached: the valuation, the deductions, and what each deduction is for.
A zero is permissible if that is genuinely the position, provided the basis is explained.
3. Served on the wrong person, or the wrong way
Contracts may specify who notices go to and how: named individuals or roles, addresses, and whether email counts. A notice sent to the site team when the contract names the commercial manager, or emailed where the contract requires a specific delivery system, invites an argument you will need to defend in an adjudication.
Check the notices clause once at the start of the job, put the correct route in the project’s commercial procedure, and keep proof of service every time.
4. Deducting contra charges nobody notified
Set-off and contra charges are a recurring source of invalid notices. Two things commonly go wrong:
- the charge appears for the first time in the pay less notice, when the contract required an earlier notice of intention to deduct or of the underlying breach;
- the charge is a round number with no supporting build-up.
If you intend to withhold, notify the ground when it arises, price it properly, and repeat it in the pay less notice. A late, unevidenced deduction is the weakest part of most payers’ cases.
5. Saying nothing because the account is “still being discussed”
This is a common and fatal mistake; the commercial teams are talking, a revised application is promised, everyone is being reasonable, and the deadline passes.
The discussion has no effect on the statutory timetable. Serve the notice, then carry on the conversation. A pay less notice is not an act of aggression; it is basic housekeeping.
For payees: the same list, in reverse
Every failure above is an opportunity on the other side of the account. When payment is short, check in this order:
- Was a payment notice served, and in time?
- Was a pay less notice served, and in time?
- Does the notice state a sum and the basis of it?
- Was it served as the contract requires?
- Were the deductions notified when they arose?
If the answers point to a missing or invalid notice, the sum in your application may be the notified sum, payable in full by the final date for payment.
MAG-7 manages payment cycles and notices for main contractors and subcontractors, and acts in adjudication when a notice has been missed. This article is a general explanation, not advice on any particular contract.