Smash-and-grab and true value adjudication: where things stand

In short: If the paying party fails to serve a valid payment notice or pay less notice in time, the sum in the payee’s application becomes the notified sum and must be paid. Since the Court of Appeal’s decision in S&T v Grove, a paying party that has lost a smash-and-grab must pay the notified sum before it can start a true value adjudication. Payees should make sure their applications are valid; payers should treat notice dates as immovable.

Two kinds of payment adjudication dominate construction disputes, and they work in opposite directions. One is about process; the other is about value. Knowing which one you are in, and what order they have to happen in, usually decides what you should do next.

The notified sum

The Construction Act gives every payment cycle a fixed shape. There is a due date, a final date for payment, and notices in between:

  • the payer gives a payment notice not later than five days after the due date, saying what it considers due and how it worked that out;
  • if it does not, the payee’s application (or a default payment notice) can become the notified sum;
  • the payer can still pay less, but only by giving a valid pay less notice before the deadline the contract sets.

Miss both notices and the consequence is blunt: the notified sum becomes payable in full by the final date for payment, whatever the work was actually worth.

Smash-and-grab

A “smash-and-grab” adjudication asks the adjudicator for exactly that. It is not an argument about measurement, quality or entitlement. It asks two questions:

  1. Was there a valid application or default payment notice, so that a notified sum exists?
  2. Did the payer serve a valid payment notice or pay less notice in time?

If the answer is yes then no, the adjudicator orders payment. This is why the process is fast and why the merits of the underlying account barely feature.

True value

A true value adjudication asks the opposite question: what is the work actually worth? The paying party normally brings it, to correct an overpayment produced by a missed notice.

The important point is the order. In S&T (UK) Ltd v Grove Developments Ltd the Court of Appeal held that a paying party which has lost a smash-and-grab must first pay the notified sum, and only then can it pursue a true value adjudication. The immediate payment obligation comes first; the true value comes second. You cannot use a true value adjudication to avoid paying in the meantime.

The practical effect is that a missed notice is expensive but not usually permanent. The money moves now, and the value can be corrected later — with the cash flow, and the commercial pressure, on the other side in the meantime.

If you are the payee

  • Make the application bulletproof. A smash-and-grab depends on the application being valid: served at the right time, in the right form, clearly an application for payment, stating the sum due and the basis of it. Most failed smash-and-grabs fail here.
  • Diarise the payer’s deadlines, not just your own. You need to know the day after which no valid notice can arrive. Our payment notice calculator works the dates out, bank holidays included.
  • Keep the evidence of service. What was sent, to whom, when, and how the contract says notices must be served.
  • Decide quickly. The right to the notified sum is strongest when acted on promptly.

If you are the payer

  • Treat notice dates as immovable. A payment notice one day late is not a late notice; it is no notice.
  • Serve a pay less notice whenever there is any doubt. It costs nothing and it preserves the position.
  • State the basis of calculation. A sum with no explanation invites a challenge to the notice’s validity.
  • If a notice has been missed, get advice straight away. The options are narrow: challenge the validity of the application, challenge jurisdiction, or pay and run the true value.

Where this is less settled

The clear rule concerns interim payments. However, the same reasoning in other situations, such as final payments or applications of doubtful validity, has been tested in later cases and continues to be. If a real sum turns on it, take advice on your facts rather than on the general position.


MAG-7 prepares and presents adjudications for referring and responding parties, with fixed fees available. See adjudication representation, or the glossary entries for notified sum, smash-and-grab and true value.

This article is a general explanation of the law in England and Wales, not advice on any particular contract or dispute.